Section 01 91 23.73: Interior Finishes Commissioning – Flooring

Flooring Commissioning belongs in Division 01, General Requirements, as Section 01 91 23.73, Interior Finishes Commissioning – Flooring. It is an Owner requirement, coordinated with the Division 09 flooring sections.

Download Section 01 91 23.73 (editable Word file)

What the section contains

Part 1 – General

Part 2 – Products

Not used.

Part 3 – Execution

Flooring CxA qualifications (1.5.A)

Independence and personnel qualification requirements are listed on the Providers page.

Defined terms (1.2.A)

Flooring Commissioning Authority (Flooring CxA)
Qualified firm engaged by Owner to verify flooring installation compliance through observation and documentation.
Requirements Alignment
Reconciles the Contract Documents, the approved flooring submittals, and the manufacturer's instructions for each flooring type prior to installation, reporting items not in agreement to the Owner, Architect, and Contractor.
Continuous Monitoring
Unattended, automated recording of ambient air conditions at fixed intervals established in the Commissioning Plan, maintained without interruption throughout the monitoring period. Manual or spot readings do not constitute Continuous Monitoring.
Hold Point
A point when the Work is not to proceed until Flooring CxA verification is documented and the Notice of Verified Readiness is issued.
Notice of Verified Readiness
Written notice issued by Flooring CxA documenting that preinstallation verification is complete for a designated area and flooring type, with verified compliance of substrate testing, substrate condition, and material acclimation to the Contract Documents, approved submittals, and manufacturer's instructions. The notice does not constitute approval or acceptance of the Work.

Reference standards (1.2.B)

Specification guidance